How to estimate a software project as a team, from first list to honest range.
A team's estimate of a software project should be a range with its assumptions written down, not one number from whoever happens to be writing the proposal. The method fits on a page: list the work, including the work nobody claims; have the people who will build it vote before they hear each other; talk only where the votes disagree; then turn the result into a range. This guide walks through each step and follows an invented team from a blank page to "10 to 16 weeks".
Why project estimates go wrong before anyone picks a number
Overruns are the normal case. A 2003 review of surveys by Moløkken and Jørgensen found that 60 to 80% of software projects overran on effort or schedule, with an average effort overrun of about 30 to 40%. Those surveys are old, but anyone who has shipped software will recognise the pattern. Three causes come up again and again:
- One person estimates everyone's work. The hard part of a job is easiest to see from inside it, so other people's work tends to look smaller than it is.
- Some work belongs to nobody. Environments, data migration, the accessibility pass and the handover don't appear in a feature list, so they don't appear in the estimate.
- One number hides what you don't know. "12 weeks" reads the same whether the team understands the work or is guessing.
The first number in the room bends every number after it
Getting more people involved only helps if they think independently. In a University of Toronto study by Jorge Aranda and Steve Easterbrook (also a 2005 conference paper), 23 people estimated the same project from the same brief. One sentence changed. A client manager, who said they had no experience with software projects, either offered no guess or guessed 2 or 20 months:
| What the manager said | Mean estimate |
|---|---|
| "About 2 months" | 6.8 months |
| No guess | 8.3 months |
| "About 20 months" | 17.4 months |
It's a small study, and the gap between the 2-month group and the no-guess group wasn't statistically significant. The high guess, though, clearly moved the estimates, and the pattern held among the 57% of participants with real estimating experience. They had been told plainly that the guess came from someone who didn't know. It moved them anyway.
So the rule for a team estimate is simple: nobody hears a number until they've committed to their own. That includes "the client is hoping for about three months" in the invite. Share the budget and the deadline after the vote, then compare them with what the team found.
Voting apart isn't the end of it, because the conversation afterwards does its own work. A 2007 study of one real project by Moløkken-Østvold and Haugen found that planning poker's agreed estimates were less optimistic and more accurate than a mechanical combination of the same people's individual estimates. Tasks estimated by individual experts in the same project were about as accurate, so the cards aren't magic. What they give you is a way to bring many people's knowledge into one estimate without letting the first speaker set it.
A project isn't just a big sprint
If you already run planning poker, the habits carry over, but a few things change at the scale of a whole project:
| A sprint | A whole project | |
|---|---|---|
| What you vote on | Refined stories | Chunks of work, up to about two weeks each |
| Unit | Story points | Person-days, unless you have a velocity to convert points with |
| Who votes | The team | Whoever will build it, or the closest people you have |
| What comes out | A plan for two weeks | A range and a list of assumptions |
The unit deserves a word. We usually argue for story points over hours, because a stable team can turn points into time with its velocity. A project often has no such history: the team may be new, or the work unlike anything they've done. If somebody needs a date or a budget, estimate in person-days and say so. If your team has a velocity that fits this kind of work, use points.
The method in six steps
1. List the work, then the work nobody claims
Break the project into chunks a person could finish in about two weeks at most, usually 15 to 40 lines. Anything larger is hiding decisions. Then read this list against yours and add what's missing:
- Environments, CI and monitoring
- Data migration and redirects from the old system
- Testing, an accessibility pass and a security review
- Analytics, documentation and support material
- Demos, feedback rounds and the changes they cause
- Launch, handover and the weeks of fixes after it
2. Write down what you're assuming
Before anyone votes, write a short "in scope, out of scope, assumed" note. It doesn't need to be complete; the vote will show you what it missed. It gives voters the same starting picture, and it becomes half of what you hand over at the end.
3. Choose who votes, and who only watches
Ask the people who will do the work. If they aren't known yet, ask the people closest to it. A sponsor, an account lead or a manager who won't build anything should watch, not vote: their number carries too much weight and too little detail. If a discipline has only one person, get a second voter on its riskiest lines. One person's estimate can't disagree with anything.
Split stories into up to six disciplines, like FE, BE and QA. Each gets its own vote, and the list keeps a total per discipline. Anyone not voting can join as a spectator and watch from the same link.
4. Vote blind, on your own time
A full project list is too long for one sitting. Run the first pass asynchronously, so people can read each line, check the code and vote when they have a quiet half hour. Alongside the estimate, ask two questions: how risky is this, and how clear is it? Those answers do most of the work in step 6.
In an async room, each person votes in their own time and the cards stay hidden until a host or facilitator reveals them. Add the Risk and Clarity questions when you create the room. Import the list from a CSV, Jira, Linear, Trello, Asana or GitHub.
5. Meet only about the disagreements
Reveal each line, accept the lines where the votes sit within one step, and spend the meeting on the rest. A wide gap rarely means someone can't estimate. It usually means people pictured different work, and the conversation will end in one of three ways:
- A hidden task. Split it into its own line and vote on it.
- A scope question. Get an answer, or pick one, and write it down as an assumption beside the line.
- Something nobody knows yet. Add a short, timeboxed spike to find out, and keep the line marked as high risk until you have.
Don't average a wide gap. A 5 and a 13 are two descriptions of the work, and 9 describes neither. Reading the shape of a reveal covers this in more detail.
6. Turn the cards into a range
The low end is the plain sum of the agreed estimates: the project if every line goes as voted. For the high end, multiply each line by a factor for its risk:
| Risk | High end | Typical line |
|---|---|---|
| Low | Estimate × 1.25 | You've built this before |
| Med | Estimate × 1.5 | Familiar work with some unknowns |
| High | Estimate × 2 | A third party, old data or an open question |
These factors are our suggested starting point, not a research finding. Replace them with your own once you've compared a few estimates with what really happened. Timeboxed spikes keep their number at both ends, because a timebox stops when the time is up.
Finally, convert days to calendar time per discipline, not for the team as a whole. The busiest discipline sets the date, as the worked example shows.
A worked example: a customer portal
An invented team of four builders (one frontend developer, two backend developers and one QA engineer) is asked how long a self-service customer portal will take. Their product manager runs the room and doesn't vote. They use the modified Fibonacci deck with each card meaning person-days, split the work into FE, BE and QA, and answer Risk and Clarity on every line.
The first pass turned up three things:
- A hidden task. The backend votes on support tickets came in at 5 and 13. The 13 had noticed attachments in the mockups, which need storage and virus scanning. Attachments became their own line, and tickets settled at 5.
- A hidden assumption. Data migration drew the same 5 and 13. One developer pictured importing current customers. The other pictured moving the full invoice history and re-running it until the totals matched. The sponsor confirmed the history had to move, so the line stayed at 13 with an assumption beside it: one cutover weekend, no period with both systems running.
- A real unknown. Most of the team answered "Vague" on admin screens, because nobody had decided whether support agents need different roles. That became a two-day spike, and the screens stayed at High risk until it was done.
Here's the estimate that came out, with each high end rounded up to a whole day:
| Line | FE | BE | QA | Days | Risk | Range |
|---|---|---|---|---|---|---|
| Sign-in and accounts | 3 | 5 | 2 | 10 | Low | 10–13 |
| Invoices and downloads | 5 | 8 | 3 | 16 | Low | 16–20 |
| Support tickets | 5 | 5 | 2 | 12 | Med | 12–18 |
| Ticket attachments | 2 | 5 | 1 | 8 | Med | 8–12 |
| Billing provider sync | 2 | 13 | 5 | 20 | High | 20–40 |
| Data migration | 0 | 13 | 5 | 18 | High | 18–36 |
| Admin screens | 5 | 3 | 2 | 10 | High | 10–20 |
| Admin roles spike | 0 | 2 | 0 | 2 | Timebox | 2–2 |
| Environments, CI, monitoring | 0 | 8 | 0 | 8 | Low | 8–10 |
| Launch, docs, handover | 3 | 5 | 5 | 13 | Med | 13–20 |
| Total | 25 | 67 | 25 | 117 | 117–191 |
Two things stand out:
- The checklist paid for itself. The last two lines came from step 1 and hold 21 of the 117 days. A feature list alone would have left them out.
- The range passes a sanity check. Its midpoint, 154 days, sits about 32% above the plain sum, close to the average overrun in the review we started with.
Now the calendar. At the usual focus of about 70%, four people deliver 2.8 person-days per working day, so 117 to 191 days looks like 8 to 14 weeks. But that treats everyone as interchangeable. The backend work alone is 67 days, or about 109 at the high end, and two developers at 70% deliver 1.4 days per working day. That's 10 to 16 weeks, and it's the honest answer, because the frontend developer can't take over the billing sync.
Hand over the range, and keep it alive
What the sponsor receives is short:
"10 to 16 weeks with this team. This assumes one cutover weekend, all invoice history moved, and no period with both systems running. Admin roles are still open; we'll know more after a two-day spike, and we'll update the range then."
The width of the range is information. Billing sync and migration account for most of it, so those are the lines to tackle first if someone wants a narrower answer. Vote again when a spike finishes, an assumption breaks or a milestone lands, and tell the sponsor when the range moves.
When the project ends, compare each line with what it actually took. Which lines ran over, and what risk had you given them? That's how the multipliers become yours. You can read more about habits that spoil estimates before the next round.
What Estimay does here, and what it doesn't
Estimay handles steps 3 to 5: hidden votes, async rounds, disciplines, the Risk and Clarity questions, spectators, and revotes once the team has talked. After a reveal it saves the smallest card at or above the average, which suits the lines within one step. On a wider gap, talk first and revote, or have the host set the estimate by hand.
It doesn't calculate ranges or calendar dates, and it doesn't track the time work really takes. Download the results as a CSV, with the answers to your extra questions as columns, and do step 6 in a spreadsheet. In a split room Risk is answered per discipline, so take the most worrying answer for the line, as the example does, or multiply each discipline on its own. An async room is deleted 30 days after it was last used, so keep the file.
Project estimation FAQ
Can you use planning poker to estimate a whole project?
Yes, once the project is broken into chunks. Voting works on any list of work. Use larger chunks than in a sprint, a deck with big enough cards, and an async first pass so nobody has to sit through 40 lines in one meeting.
How many people should estimate a software project?
Everyone who will build a significant part of it, which for most projects means three to seven voters. Fewer than three and there's little to compare. For more than seven, the async first pass matters even more.
How long does a team estimate take?
For about 30 lines, plan on 30 to 45 minutes per person for the async pass and one meeting of about an hour for the disagreements. Writing the list and the assumptions beforehand usually takes longer than either.
What if the client or sponsor wants one number?
Give the range first and explain what would narrow it. If a contract really needs one number, choose it from the upper half, write the assumptions beside it, and say what happens when one breaks. If the number has to come down, cut scope openly. Don't shave the team's estimates.
Should the tech lead vote?
Yes, if they'll build part of it, and on the same terms as everyone else: hidden until the reveal. If people tend to follow a senior colleague even after the cards flip, use an anonymous room, which shows how many people picked each card but not who.
Estimate your next project together. Create an async room, add your list and share the link. No sign-up needed.